Financing burden of CPEC


ISHRAT HUSAIN — UPDATED about 5 hours ago
 WHATSAPP 25 COMMENTS EMAIL PRINT

The writer is former governor of the State Bank of Pakistan.
The ongoing debate on the impact of CPEC projects on future external payments’ obligations is welcome, but should be informed by analysis based on facts rather than opinion.

The total committed amount under CPEC of $50 billion is divided into two broad categories: $35bn is allocated for energy projects while $15bn is for infrastructure, Gwadar development, industrial zones and mass transit schemes. The entire portfolio is to be completed by 2030. Therefore, the implementation schedule would determine the payments stream. Energy projects are planned for completion by 2020, but given the usual bureaucratic delays, it won’t be before 2023 that all projects are fully operational. Under the early harvest programme, 10,000 MW would be added to the national grid by 2018. Therefore, the disbursement schedule of energy projects is eight years (2015-2023). Infrastructure projects such as roads, highways, and port and airport development, amounting to $10bn, can reasonably be expected to be concluded by 2025, while the remaining projects worth $ 5bn would spill over into the 2025-30 period.

Examine: Hidden costs of CPEC

Given the above picture, it is possible to prepare a broad estimate of the additional burden on Pakistan’s external payment capacity in the coming years. As the details of each project become available, the aggregate picture can be refined further. The margin of error would not cause significant deviation.

It is possible to prepare an estimate of the additional burden on our external payments’ capacity.
The entire energy portfolio will be executed in the IPP mode —as applied to all private power producers in the country. Foreign investors’ financing comes under foreign direct investment; they are guaranteed a 17pc rate of return in dollar terms on their equity (only the equity portion, and not the entire project cost). The loans would be taken by Chinese companies, mainly from the China Development Bank and China Exim Bank, against their own balance sheets. They would service the debt from their own earnings without any obligation on the part of the Pakistani government.

Import of equipment and services from China for the projects would be shown under the current account, while the corresponding financing item would be FDI brought in by the Chinese under the capital and finance account. Therefore, where the balance of payments is concerned, there will not be any future liabilities for Pakistan.

To the extent that local material and services are used, a portion of free foreign exchange from the FDI inflows would become available. (Project sponsors would get the equivalent in rupees). For example, a highly conservative estimate is that only one-fourth of the total project cost would be spent locally and the country would benefit from an inflow of $9bn over an eight-year period, augmenting the aggregate FDI by more than $1bn annually. This amount can be used to either finance the current account deficit or reduce external borrowing requirements. Inflows for infrastructure projects for local spending would be another $4bn over 15 years.

Taking a highly generous capital structure of 60:40 debt-to-equity ratio for energy projects, the total equity investment would be $14bn. Further, assuming the extreme case that the entire equity would be financed by Chinese companies (although this is not true in the case of Hubco and Engro projects, where equity and loans are being shared by both Pakistani and Chinese partner companies) the 17pc guaranteed return on these projects would entail annual payments of $2.4bn from the current account.

CPEC’s second component, ie infrastructure, is to be financed through government-to-government loans amounting to $15bn. As announced, these loans would be concessional with 2pc interest to be repaid over a 20- to 25-year period. This amount’s debt servicing would be the Pakistan government’s

This entry was posted in: Uncategorized

by

Vision 21 is Pakistan based non-profit, non- party Socio-Political organisation. We work through research and advocacy for developing and improving Human Capital, by focusing on Poverty and Misery Alleviation, Rights Awareness, Human Dignity, Women empowerment and Justice as a right and obligation. We act to promote and actively seek Human well-being and happiness by working side by side with the deprived and have-nots.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s